![]() |
||||
|
|
|
|||
|
|
|
|||
![]() |
Our Programmes Oil and Gas Visit the Archives.Back to Current Articles. #3-4807
49th Street Yellowknife
NT X1A
3T5 March
8, 2002 Todd Burlingame, Chairperson Mackenzie Valley Environmental Impact Review Board Box 938 Yellowknife NT
X1A 2N7 Melody McLeod, Chairperson Robert Hornal, Chairperson Mackenzie Valley Land and Water Board Environmental Impact Review Board Box 2130 Box
2120 Yellowknife NT
X1A 2P6 Inuvik
NT X0E 0T0 Willard Hagen, Chairperson Larry Wallace, Chairperson Gwich’in Land and Water Board Sahtu Land and Water Board Box 2018 Box
1 Inuvik NT X0E
0T0 Fort
Good Hope NT X0E 0H0 Gordon Wray, Chairperson Kenneth Vollman, Chairperson NWT Water Board National
Energy Board Box 1500 444
Seventh Avenue Yellowknife NT
X1A 2R3 Calgary
AB T2P 0X8 Sid Gershberg, President Canadian Environmental Assessment Agency SW 200 Sacré-Coeur Blvd., 14th Floor Hull QC K1A
0H3 Re: Draft
Cooperation Plan
Dear Board
Chairs and Agency President The
Canadian Arctic Resources Committee (CARC) is pleased to submit the following
comments on the Draft Cooperation Plan released on January 7, 2002. We would like to commend the Boards and
Agency for taking the initiative to create a cooperation plan and for the
opportunity to review the draft. We
recognize the significant amount of work that has been done to date. Although
it is not stated anywhere in the Plan or the accompanying press release, it is
our understanding, after discussions with the staff of the Mackenzie Valley
Environmental Impact Review Board, that there is a public registry for comments
submitted. We believe this is a wise
step and that this should continue and be made known to the public. Each Board and Agency may wish to establish
a public registry, at least for the purposes of completing the Cooperation
Plan. We would appreciate a written
response to our submission and that reasons or a detailed response be prepared
for revisions that may be made to the Plan, so that these may be added to the
public registry. CARC
supports, in principle, the concept of a coordinated joint panel for a
potential pipeline application in the Mackenzie Valley. We simply wish to ensure that such a process
is rigorous, comprehensive, fair and transparent. The magnitude of a potential Mackenzie Valley pipeline demands a
thorough review where the need for the project and alternatives to the project,
and cumulative effects are examined in detail. All of the activities that will
go into filling the pipeline, and keeping it filled, must be included in the
scope of the project assessed. We believe
that it is prudent to conduct a very thorough environmental assessment followed
by established regulatory processes including water licencing, issuance of land
use permits and other approvals. The
environmental assessment must seriously consider the “no go” option and not
leave any major issues to be resolved in the regulatory process, as was the
case with both the BHP and Diavik diamond mines. We have
attached a detailed set of comments on the draft Plan. Our major concerns with the draft Cooperation
Plan are as follows: ·
a lack of clarity in defining the role of the
National Energy Board in the joint panel
process with the potential for a separate process that will likely
results in overlap, duplication and inefficiency; ·
the substance of the Plan does not adequately reflect
the purpose and objectives set out, particularly for effective public
participation; ·
the public registry requirements need clarification
and a commitment towards a joint public record for the environmental assessment
and regulatory proceedings would be most beneficial; ·
the issue of participant or intervenor funding has
not been adequately addressed; ·
the preliminary information requirements do not
provide adequate detail to enable a proper scoping of the project as regards
cumulative effects; and ·
a process to develop panel procedures has not been
articulated and further public participation and comment on these would be in
order. We hope
that you are open to the constructive suggestions we have offered and would
welcome the opportunity to discuss any of our concerns with you. Sincerely, Kevin
O’Reilly Research
Director cc. Hon. Robert Nault, Minister of Indian
Affairs and Northern Development Hon.
David Anderson, Minister of Environment Hon.
Ralph Goodale, Minister of Natural Resources Hon.
Ethel Blondin-Andrew, MP Western Arctic Hon.
Stephen Kakfwi, NWT Premier Grand
Chief Mike Nadli, Deh Cho First Nations Edwin
Erutse, Chairperson, Sahtu Secretariat Inc. Fred
Carmichael, President, Gwich’in Tribal Council Nellie
Cournoyea, Chair, Inuvialuit Regional Corporation COMMENTS ON THE DRAFT COOPERATION PLAN
SUBMITTED BY THE CANADIAN ARCTIC RESOURCES COMMITTEE
Introduction
1.2 Purpose
and Objectives of the Cooperation Plan The
objectives laid out are not as detailed as those in the enabling legislation of
many of the potential parties to the Plan.
For example, the purposes of Part 5 of the Mackenzie Valley Resource Management Act (MVRMA), s. 114, include “to ensure that the impact on the
environment of proposed developments receives careful consideration before
actions are taken in connection with them” and “to ensure that the concerns of
Aboriginal people and the general public are taken into account”. There may be similar purposes and objectives
laid out in other applicable legislation that should be summarized in this
section. 1.3 Scope of
the Cooperation Plan It should be mentioned here that the Deh Cho First
Nations (as opposed to the “Nation” referred to in Table 1) were only invited
to send a representative part way through the process similar to the footnote
for the Yukon Government participation.
To the best or our knowledge, the Deh Cho First Nations have not
consented to this process and there may be unfulfilled fiduciary obligations on
the part of the Crown. Context for Natural Gas Development in the NWT 2.1
Development Scenarios Although it is clearly not the intention of the
Agencies to set out the scope of the project in this section, the descriptions
are limited to the immediate pipeline and development of initial production
capacity. Some regard should be shown
towards later exploration and development that will be needed to keep the
pipeline and production facilities working at capacity or in an efficient
manner. It may be desirable here to
suggest that scenarios will likely be required to fully scope the project and
ensure that there is an adequate cumulative effects assessment. Table 2 does not specify a role for the Government of
the Northwest Territories (GNWT) that is covered by the MVRMA. GNWT Ministers can
become a “responsible minister” under the MVRMA,
and triggers exist under GNWT legislation for environmental assessment in
general. Some consideration should be
given to listing other federal agencies that have regulatory authority
including the Department of Fisheries and Oceans and Natural Resources Canada,
similar to the listing in Table 2 for DIAND. 3.1 Rationale
for the Selection of the Cooperation Framework The text refers to several options, ranging from a
combined environmental assessment and regulatory process to a variety of other
less integrated configurations. More
detail on these options would have been helpful in promoting public discussion. It would have been preferable, in our view,
to structure the Plan as a more fully integrated process which would ensure no
duplication of effort and consistent application of the results of the EIA in
the regulatory process. 3.2 Guiding
Principles The Diavik Comprehensive Study was supposed to be a
“made in the north” process, but it resulted in litigation and unfulfilled
commitments on cumulative effects assessment and management. We are concerned that steps be taken to
avoid these problems as part of the Cooperation Plan. One of the principles mentioned here, “enhanced
public participation” is not reflected in the Plan, as the process simply meets
the minimum public participation requirements set out in legislation. It would be more appropriate to present
measures that reflect the most rigorous of all the public participation
provisions and procedures specified in applicable legislation (e.g.
cross-examination of technical experts).
Consideration should be given to additional
principles including Canada’s international and treaty obligations, and the
precautionary principle. The Great
Whale, BHP and Voisey’s Bay panels all required that Traditional Knowledge
should be given full and equal consideration.
These precedents could be recognized in this section of the draft
Cooperation Plan. See discussion above under s. 2.1. It is unclear from the balance of the draft
Plan how some objectives, such as “addressing the importance of traditional
knowledge in the EIA and regulatory processes” will be attained. 3.4
Assumptions There appears to be an unstated assumption that the
NEB processes cannot be fully integrated with the joint panel process. The role of the NEB in a joint panel should
be clearly spelled out. The NEB is required to examine issues such policy
issues as the availability of gas for a pipeline, existence of markets,
economic feasibility, and the broader public interest in granting or refusing
an application (see s. 52 of the National
Energy Board Act). If the NEB is
not part of the joint panel process, this may essentially lead to a separate
re-examination of the need for the project.
The NEB will also examine and select routing for a pipeline, most
appropriate construction methods and timing of construction (s. 36 NEBA), matters that would be examined
during consideration of alternatives in the earlier joint panel process. This
has the potential again for duplication and inefficiency if the NEB is not part
of a joint panel process. The NEB
requirements are also briefly summarized on page 17 (paragraph 3) of the draft
Cooperation Plan. It is difficult to see how the draft Cooperation Plan
reflects the spirit or intent of the December 4, 2000 Memorandum of
Understanding between the MVEIRB and NEB with the potential separation of the
NEB regulatory process from the joint panel.
At a minimum, one positive measure that could easily be implemented,
would be a joint single public record or registry for all environmental assessment
and regulatory processes. This may help
eliminate duplication and ensure that there would not be a need to present
expert evidence in two different proceedings.
It would also ensure that all expert evidence could be tested in a
rigorous manner and receive similar consideration by all the Agencies. At the end of a joint panel process, only the
recommendations are to go forward to the NEB and other regulatory bodies. We would like to see some stronger
assurances that recommendations from the joint panel make their way into
regulatory terms and conditions. Although it is not stated, we presume that the
Preliminary Information Package that may be submitted by a proponent will be a
public document and placed on the appropriate public registries. The Minister(s) may also have the ability to
refer matters back to a joint panel that they may request for reconsideration
(see MVRMA s. 135(1)(a) and
137(1)(a)). 3.5
Highlights of the Cooperation Framework A single record for all proceedings, both for the
environmental assessment and regulatory proceedings should be considered as
discussed above. There should be one
set of procedures developed for both the environmental assessment and
regulatory proceedings and it should be developed to meet the highest standards
set out in legislation. We would
strongly urge that there be public involvement in the development of the
procedures. 3.6.1
Description of Cooperation Framework Phases There should be opportunities for public involvement
and review of the three agreements specified in this section and of the
consolidated information requirements.
The technical support mentioned should be accessible to the public and
subject to the public scrutiny provisions set out in procedures for the
processes. 3.6.2
Preliminary Information Package The PIP requirements do not appear to be
comprehensive enough to permit a scoping decision to be made, particularly as
regards cumulative effects. In section
3.6.2 of the Plan, it is clear that the PIP is intended to provide this
information. Section 16(1)(e) of CEAA requires the assessment of factors
such as “the need for the project and alternatives to the project”, which are
very real considerations here, where the potential for competing proposals
exists. Further development of the PIP
at this time would be in order. 3.6.3
Application One of the most crucial steps in this section will be
the scoping of the project. There needs
to be a clear role for the public in scoping of the project as laid out in the MVRMA s. 117(2)(a). It is our view that the scope of the project
should not be limited to the immediate pipeline and field development.
Scenarios or conceptual plans should be developed for all of the activities
that will go into keeping a pipeline filled for a reasonable period of time,
given the life-cycle of a any pipeline project of this magnitude. These activities should be included in the
scope of the project and process should be laid out for developing the scope of
the project, including opportunities for public involvement. There should be public involvement opportunities in
determining the location and requirements for a joint public record or
registries. There is no reference in this section to the case
where more than one application is filed by different proponents. What process will the Agencies use in the
event of competing proposals? Given the
very real possibility of alternate routes, this is a point that requires
clarification. The section on “Proposed Course of Action by
Regulators” refers to a team of experts serving the Boards. These experts should be available to the
public and open to questioning as set out in the applicable procedures. The Boards may need to retain separate
experts at various times if there are competing mandates and interests. Given the clear linkages and overlap between
the proposed environmental assessment and regulatory processes, it is essential
that participant funding be extended to the regulatory phase even where there
may be no legal requirement to do so. The “Estimated Timeframe” section refers to the
possibility that the MVEIRB may identify public concern as the basis for an
environmental impact review.
Significant adverse impacts can also serve as the trigger for an order
for an environmental impact review (MVRMA
s. 128(1)(b)(i)). This section does
not make reference to the possibility that the MVEIRB may find that the MVEIRB
may recommend the rejection of a proposed development (MVRMA s. 128(1)(d)). 3.6.4 Joint
EIA Panel Hearings Coordinated with Regulatory Hearings We would strongly urge that the public have the
opportunity to participate in the conformity review of any environmental
assessment documentation submitted by the proponent and government. The public should also have the ability to
request relevant additional information. There is very little detail on participant funding in
this section. Participant funding
appears to be limited to the presentation of “views to the Joint EIA
Panel”. We would strongly urge that
participant funding be made available for the scrutiny of the proposal’s
compliance with consolidated information requirements, of proponent and
government evidence and the preparation and presentation of independent expert
testimony and materials. As mentioned above, participant funding should be
extended to include the regulatory process.
Participant funding should be made available at the earliest possible
time to ensure there is the opportunity for informed public input into the
review of the formal agreements amongst the Agencies, scoping of the project,
rules of procedure and other important steps identified in the Preparation
Phase. Potential intervenors should be involved in the
process for determining the access to and amounts of participant funding. While this may be outside the jurisdiction
of the Agencies and primarily the concern of DIAND, this issue will be critical
to the success of a coordinated assessment and regulatory process. For the Royal Commission on Aboriginal
Peoples, Justice Brian Dixon was retained as an independent advisor to provide
advice on the amount and allocation of funding to organizations wishing to
participate in the Commission’s proceedings.
A similar process, along with some meetings of potential intervenors
would facilitate the identification of an appropriate funding level and access
procedures. A separate funding
application review committee can be established later to allocate the available
funds applying the access procedures as is done now for CEAA panels. The need
for intervenor funding is growing given the declining capability of governments
to bring forward independent technical expertise. We have noted that DIAND has recently provided $4.2 million to
the Inuvialuit Development Corporation for new drill rigs and a support camp in
the Mackenzie Delta. While CARC
supports economic diversification and maximization of northern benefits, there
needs to be a fair, rigorous and comprehensive review of any pipeline project
with an adequate level of participant or intervenor funding. We are concerned at this point that there may not be
sufficient funds for meaningful public participation. It will take very significant resources to mount an effective
intervention in a project of the magnitude of a Mackenzie Valley pipeline. As an example, the environmental
organizations (as coordinated by CARC) total participant funding ($29,000) and
in-kind contributions towards the BHP Panel review was in excess of
$250,000. We have not estimated a
budget for an intervention in a Mackenzie Valley pipeline as of yet, but it
would be safe to say it would be significantly more than our efforts during the
BHP Panel process. Our comments above on the desirability of a joint
public record or registry for the entire environmental assessment and
regulatory proceedings are discussed above. The flow charts shown in Figures 1 and 2 make no
provision for ‘no-go’ recommendations or decisions. 3.6.5
Completion of Regulatory Processes Please note our comments above on the need and
desirability for consistent procedures, participant funding and a joint public
record or registry. Several regulatory approvals are mentioned in this
section that do not require a public hearing.
The joint panel process should determine whether they should be issued
and whether terms and conditions that should be attached to these approvals. Prepared by:
Canadian Arctic Resources Committee Date: March 8, 2002 |
|
||
|
|
||||
|
|
|
|
|
|